1er juillet 2014

Update on construction of access road
Construction of access to the Grande Chaloupe site consists in reorganising and improving the existing entrances and exits of the RN1 (Maine Road) in the sector. These works will consist in :

On the cliff side : creation of an exit road upstream of the existing crossroads, as well as modification of the crossroads to provide an entrance in the direction of Saint Denis,

On the sea side : enlarging the existing entrance/exit road, making safer the entrance in the direction of la Grande Chaloupe and the exit in the direction of La Possession.

These works are considered as normal maintenance, having a limited direct effect on the main flow of traffic on the RN (main road).

Planned start of construction : end of 2013 (duration of construction work : 4 months, with two months of preparation)

Cost of works : €345, 000 incl. tax

Construction to be carried out by SAS