Construction schedules

1er juillet 2014

2013 :
-  End of administrative and legal procedures

Beginning 2014 :
-  Preparatory work for construction site access – temporary interchange RD41-RN1 at the La Possession end, going south
-  Preparatory work for construction site access – construction site slip-road parallel to RN1 interchange of Port Est at the entrance of the coastal Road
-  Preparatory work for construction site access – restructuring of the interchange of La Grande Chaloupe
-  Construction of the 5400 m viaduct (preparation and mobilisation of construction site equipment)
-  Construction of the first 4 sections of the dike (preparation and mobilisation of construction site equipment)

During 2014 :
-  Construction of the interchange of La Possession
-  Construction of the viaduct of La Grande Chaloupe